Puget Sound Energy, Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/22/2007, Docket: RP07-462-000, Status: Effective
Original Sheet No. 127 Original Sheet No. 127 : Effective
AMENDMENT NO. 8
to
JACKSON PRAIRIE GAS STORAGE PROJECT AGREEMENT
This Amendment is entered into as of the 16th day of May, 2007, by and
between Northwest Pipeline Corporation ("Northwest"), a Delaware corporation,
Puget Sound Energy, Inc. ("Puget"), a Washington corporation and Avista
Corporation ("Avista"), a Washington corporation, collectively "the Owners."
RECITALS:
A. WHEREAS, Northwest, Puget and Avista are parties to that certain
Jackson Prairie Gas Storage Project ("Storage Project") Agreement dated
January 15, 1998, as amended ("Agreement");
B. WHEREAS, a phased expansion of the storage capacity in the Storage
Project has been authorized, as described in a prior notice application
filed with the Federal Energy Regulatory Commission in Docket No. CP02-
384;
C. WHEREAS, the procedures applicable to the development of the
authorized phased storage capacity expansion, as set forth in Exhibit G
to the Agreement, specify that the expansion phases are based on a March
through February water withdrawal/gas injection cycle;
D. WHEREAS, Article 4.6 of the Agreement provides that interim
amendments to Exhibits C, D, E and F (as appropriate) will be made upon
completion of each phase of a phased expansion;
E. WHEREAS, the Owners desire to amend Exhibits C, D and E to reflect
the February 28, 2007 completion of the fifth phase of the authorized
storage capacity expansion;
F. WHEREAS, the Owners also desire to amend Exhibits C, D and E to
reflect the 900,000 Mcf reduction of Project Cushion Gas Requirement and
total Project Gas Capacity resulting from the permanent loss of cushion
gas since the inception of the Storage Project as determined by the
Operator, consistent with the certificate authorization in Docket No.
CP06-465;
G. WHEREAS, the Owners desire to amend Exhibit G to recognize that
the storage capacity expansion authorized in Docket No. CP02-384 is now
anticipated to be completed no later than March 1, 2012, instead of no
later than November 1, 2008; and