Exhibit C
(revised May 26, 2005, pursuant to Amendment No. 6)
to the
Jackson Prairie
Gas Storage Project Agreement
Certificated Characteristics and Capabilities
Characteristics and Capabilities of the Jackson Prairie Storage Project for
the 2005-2006 Storage Cycle and thereafter:*
Project Cushion Gas Requirement Not less than 20,585,155 Mcf
Zone 2 Not less than 16,585,155 Mcf
Zone 9 Not less than 4,000,000 Mcf
Project Working Gas Capacity Not more than 20,677,733 Mcf
Zone 2 Not more than 19,677,733 Mcf
Zone 9 Not more than 1,000,000 Mcf
Project Gas Capacity Not more than 41,262,888 Mcf
Zone 2 Not more than 36,262,888 Mcf
Zone 9 Not more than 5,000,000 Mcf
Project Firm Withdrawal Deliverability Not more than 850,000 Mcf Daily
Project Best Efforts Deliverability Not more than 150,000 Mcf Daily
* In addition to the stated quantities, the certificated Characteristics and
Capabilities of the Jackson Prairie Storage Project include any portions of
the expanded cushion and working gas capacities developed, month to month,
during the current water withdrawal/gas injection cycle of the 2002-2008
Expansion Project described in Exhibit G.