Puget Sound Energy, Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/24/2004, Docket: RP04-305-000, Status: Effective
Original Sheet No. 115 Original Sheet No. 115 : Effective
Exhibit D
(revised May 14, 2004, pursuant to Amendment No. 5)
to the
Jackson Prairie
Gas Storage Project Agreement
Owner's Shares of Storage Service Rights
Owner Firm Injection Capability Firm Withdrawal
Share Deliverability Share
Northwest 1/3 1/3
Avista 1/3 1/3
PSE 1/3 1/3
PROJECT 1 1
Best Efforts Withdrawal Firm Working Gas Capacity *
Owner Deliverability Share Share
Northwest 1/3 0.3197
Avista 1/3 0.3606
PSE 1/3 0.3197
1 1
Owner Cushion Gas Requirement *
Share
Northwest 0.3243
Avista 0.3514
PSE 0.3243
PROJECT 1
* The Owner's Shares are the stated shares adjusted, as necessary, to reflect
the respective participation levels by the Owners in the expanded cushion and
working gas capacities developed, month to month, during the current water
withdrawal/gas injection cycle of the 2002-2008 Expansion Project described in
Exhibit G.