Puget Sound Energy, Inc.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/24/2004, Docket: RP04-305-000, Status: Effective

Original Sheet No. 114 Original Sheet No. 114 : Effective

 

 

Exhibit C

(revised May 14, 2004, pursuant to Amendment No. 5)

to the

Jackson Prairie

Gas Storage Project Agreement

 

Certificated Characteristics and Capabilities

 

Characteristics and Capabilities of the Jackson Prairie Storage Project for

the 2004-2005 Storage Cycle and thereafter:*

 

Project Cushion Gas Requirement Not less than 20,178,680 Mcf

 

Zone 2 Not less than 16,178,680 Mcf

 

Zone 9 Not less than 4,000,000 Mcf

 

Project Working Gas Capacity Not more than 20,068,020 Mcf

 

Zone 2 Not more than 19,068,020 Mcf

 

Zone 9 Not more than 1,000,000 Mcf

 

Project Gas Capacity Not more than 40,246,700 Mcf

 

Zone 2 Not more than 35,246,700 Mcf

 

Zone 9 Not more than 5,000,000 Mcf

 

Project Firm Withdrawal Deliverability Not more than 850,000 Mcf Daily

 

Project Best Efforts Deliverability Not more than 150,000 Mcf Daily

 

 

* In addition to the stated quantities, the certificated Characteristics and

Capabilities of the Jackson Prairie Storage Project include any portions of

the expanded cushion and working gas capacities developed, month to month,

during the current water withdrawal/gas injection cycle of the 2002-2008

Expansion Project described in Exhibit G.