Puget Sound Energy, Inc.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 11/01/1998, Docket: CP98-250-002, Status: Effective

Original Sheet No. 84 Original Sheet No. 84 : Effective



Exhibit C


(dated January 15, 1998)


to the


Jackson Prairie

Gas Storage Project Agreement



Certificated Characteristics and Capabilities




Characteristics and Capabilities of the Jackson Prairie Storage

Project for the 1997-1998 Storage Cycle and thereafter:


Project Cushion Gas:


Zone 2 Not less than 17.2 Bcf


Zone 9 Not less than 2.0 Bcf


Project Working Gas Capacity:


Zone 2 Not more than 15.1 Bcf


Project Total Storage Gas Capacity:


Zone 2 Not more than 34.4 Bcf


Project Firm Withdrawal Deliverability: Not more than 550,000 Mcf





Project Best Efforts Deliverability: Up to 71,800 Mcf Daily