Puget Sound Energy, Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1998, Docket: CP98-250-002, Status: Effective
Original Sheet No. 82 Original Sheet No. 82 : Effective
Exhibit A
(dated January 15, 1998)
to the
Jackson Prairie
Gas Storage Project Agreement
Description of the Project
The Storage Project includes Storage Reservoirs, with certificated
characteristics and capabilities as outlined on Exhibit C, along
with all associated properties and facilities. The major plant
facilities in the Storage Project include:
(1) compressor units--three Solar Saturn T-1000 gas turbines,
one Solar Saturn T-1300 gas turbine, two Solar Centaur T-4700 gas
turbines, and three Waukesha reciprocating engines;
(2) dehydration units and gas cooling units adjacent to the
compressors;
(3) bi-directional meter station, including four 12-inch turbine
meters, adjacent to Northwest's Natural Gas Transmission System;
(4) parallel 14-inch, 16-inch and 20-inch transmission lines
extending from the compressors to the meter station;
(5) injection and withdrawal and observation wells, with
appurtenant wellhead separation and measurement equipment; and
(6) lateral lines extending from the injection and withdrawal
wells to the compressors.