Puget Sound Energy, Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1998, Docket: CP98-250-002, Status: Effective
Original Sheet No. 53 Original Sheet No. 53 : Effective
Project Delivery Point in quantities that do not exceed the
capabilities of the Storage Project and the Storage Service Rights
of the respective Owners. Withdrawals for an Owner will first
serve to reduce such Owner's Interruptible Working Gas Inventory,
if any. Withdrawals for an Owner other than Northwest shall not
exceed Available Working Gas Inventory of such Owner. Withdrawals
for Northwest in excess of its Available Working Gas Inventory may
be made for Northwest System Balancing and shall be reflected in
the Northwest System Balancing Account.
7.4 Force Majeure Use By Northwest
In the event of the occurrence of a "force majeure" condition, as
defined by ARTICLE 10, on Northwest's Natural Gas Transmission
System, which renders it impossible for Northwest to maintain
minimum pipeline pressures and service required to supply
contracted firm service to any of Northwest's customers, Northwest
shall have the right to withdraw working gas from the Storage
Reservoir in such quantities and at such rates as required to
restore and maintain minimum pressure and service, even though
such quantities and rates of withdrawals may be in excess of
Northwest's Storage Service Rights; provided, however, that such
withdrawals shall (i) not jeopardize the integrity of the Storage
Project, and (ii) not reduce the availability of nominated
quantities and withdrawal rates from the respective Storage
Service Rights of other Owners, except by their express
permission. Northwest shall not withdraw any cushion gas or
reduce the volume thereof below the Project Cushion Gas
Requirement, unless otherwise approved by the Committee.
Northwest shall promptly make all reasonable efforts, including,
but not limited to, enactment of allowable entitlements on its
transmission system to restore such integrity or such availability
and shall promptly restore to the Storage Project the amount of
Project Gas Inventory withdrawn by Northwest.
7.5 Nominations
Daily nominations for the use of Storage Service Rights by an
Owner shall be made to the Project Operator prior to the
commencement of that Day. Owners shall be allowed to adjust the
quantity of injection or