Puget Sound Energy, Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1998, Docket: CP98-250-002, Status: Effective
Original Sheet No. 10 Original Sheet No. 10 : Effective
in Part 1 of Exhibit E as such part may be revised in accordance
with this Agreement.
1.4 Capital Costs
"Capital Costs" for the Storage Project means the capital costs of
the Storage Project calculated in accordance with the Uniform
System and generally accepted accounting principles for gas
utilities.
1.5 Chehalis Farm Tap
The "Chehalis Farm Tap" is a transportation delivery point from
Northwest to PSE located within the Storage Project.
1.6 Committee
"Committee" means the management committee created pursuant to
ARTICLE 5.
1.7 Confirmed Nomination
"Confirmed Nomination" means any and all volumes of natural gas
nominated for injection into or withdrawal from the Storage
Project provided that (i) such nominating Owner has such
quantities available for delivery; (ii) such nominations do not
exceed the applicable Storage Service Rights of the nominating
Owner; (iii) such nomination does not exceed the capability of the
Storage Project for such Day; and (iv) Northwest has confirmed any
necessary corresponding nominations for related transportation
services on Northwest's Natural Gas Transmission System. Any
differences between aggregate Confirmed Nominations for all other
Owners other than Northwest and the actual aggregate metered
injections or withdrawals for a given Day will be deemed to be
Confirmed Nominations for Northwest's use of the Storage Project.