Viking Gas Transmission Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2009, Docket: RP09-807-000, Status: Effective
Fifth Revised Sheet No. 89 Fifth Revised Sheet No. 89
Superseding: Fourth Revised Sheet No. 89
FIRM TRANSPORTATION AGREEMENT
Rate Schedule FT-A
ARTICLE II - TRANSPORTATION
Company agrees to accept and receive daily, on a firm basis, at the Receipt Point(s), from
Shipper such quantity of gas as Shipper makes available and deliver for Shipper to the
Delivery Point(s) an Equivalent Quantity of gas up to the TQ, subject to the MDQs specified
on Exhibit A for the Primary Receipt Point(s) and Primary Delivery Point(s).
ARTICLE III - RECEIPT AND DELIVERY PRESSURES
Shipper shall deliver, or cause to be delivered, to Company the gas to be transported
hereunder at pressures sufficient to deliver such gas into Company's system at the Receipt
Point(s), provided such pressure shall not exceed 877 psig. Company shall deliver the gas
to be transported hereunder to or for the account of Shipper at the pressures existing in
Company's system at the Delivery Point(s) unless otherwise specified on Exhibit A.
ARTICLE IV - QUALITY SPECIFICATIONS AND STANDARDS FOR MEASUREMENTS
For all gas received, transported and delivered hereunder, the Parties agree to the quality
specifications and standards for measurement as provided for in the General Terms and
Conditions of Company's FERC Gas Tariff. Company shall be responsible for the operation of
measurement facilities at the Delivery Point(s), the North Branch, Minnesota Receipt Point
and at any other mutually agreeable Receipt Point(s). In the event that measurement
facilities are not operated by Company, then the responsibility for operations shall be
deemed to be that of the operator of the measurement facilities at such point. If the
measurement facilities are not operated by Company and there is no third-party operator at
such point, then the responsibility for operations shall be deemed to be Shipper's.
ARTICLE V - FACILITIES
The facilities necessary to receive, transport and deliver gas as described herein
are in place and no new facilities are anticipated to be required.
or
080109