Vector Pipeline L.P.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/01/2010, Docket: RP10-678-000, Status: Effective

Fifth Revised Sheet No. 116 Fifth Revised Sheet No. 116

Superseding: Fourth Revised Sheet No. 116

 

(e) For purposes of 2(b), (c), and (d), "provide" shall mean,

for transmittals pursuant to standards 1.4.x, receipt at the

designated site, and for purposes of other forms of

transmittal, it shall mean send or post.

 

(f) At the end of each Gas Day, Transporter should provide the

final scheduled quantities for the just completed Gas Day.

With respect to the implementation of this process via the

1.4.x scheduled quantity related standards, Transporter

should send an end of Gas Day Scheduled Quantity document.

Receivers of the end of Gas Day Scheduled Quantity document

can waive the sender's sending of the end of Gas Day

Scheduled Quantity document. All nominations shall include

Shipper defined begin dates and end dates. All nominations

excluding intraday Nominations shall have rollover options.

Specifically, Shippers shall have the ability to nominate

for several Days, months, or years, provided the nomination

begin and end dates are within the term of Shipper's

contract. Nominations received after the nomination

deadline shall be scheduled after nominations received

before the nomination deadline. The receiver of a

nomination initiates the confirmation process. The party

that would receive a Request for Confirmation or an

unsolicited Confirmation Response may waive the obligation

of the sender to send. The sending party shall adhere to

nomination, confirmation, and scheduling deadlines. The

party receiving the request has the right to waive the

deadline.

 

3. Any change in a daily scheduled quantity implemented during the

Day shall only be recognized pro rata to the fraction of the Day

remaining at the time the change is implemented. Changed daily

scheduled quantity shall not exceed an amount equal to Shipper's

Contracted Capacity multiplied by the fraction of the Day

remaining at the time the changes are implemented, nor less than

zero at any point in time. Transporter shall be under no

obligation to accept such revisions for Shipper nominations made

under Transporter's Interruptible Transportation Service.

 

4. Pursuant to NAESB Standards 1.3.9, 1.3.11, 1.3.13: All

nominations, including Intraday Nominations, shall be based on a

daily quantity; thus, an intraday nominator need not submit an

hourly nomination. Intraday Nominations shall include an effective

date and time. The interconnected parties shall agree on the

hourly flows of the Intraday Nomination, if not otherwise

addressed in the Transportation Agreement or Tariff. Intraday

Nominations can be used to request increases or decreases in total

flow, changes to receipt points, or changes to delivery points of

scheduled Gas. Intraday Nominations do not rollover (i.e.,

Intraday Nominations span one Day only). Intraday Nominations do

not replace the remainder of a standing nomination. There is no

need to renominate if an Intraday Nomination modifies an existing

nomination.

 

5. Shipper Prioritization of Nominated Quantities - If Shipper elects

to nominate quantities of Gas to be received by Transporter from

one or more upstream parties at one or more Receipt Points for

delivery by Transporter to one or more downstream parties at one

or more Delivery Points for the account of Shipper, Shipper shall

provide the priority, method, and extent