Gulf South Pipeline Company L P

Sixth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 05/14/2010, Docket: RP10-601-000, Status: Effective

First Revised Sheet No. 2905 First Revised Sheet No. 2905

Superseding: Substitute Original Sheet No. 2905



Section 24




24.6 Subject to Section 24.3 above, the Requesting Customer may

construct their own interconnect facilities at their sole

expense; provided, however, such interconnecting facilities

shall meet all of Gulf South's technical and engineering

requirements. These interconnect facilities shall be built to

Gulf South's pipeline but only Gulf South shall construct the

tap, at the Requesting Customer's sole cost, to complete the