GENERAL TERMS AND CONDITIONS
Section 24
(Continued)
24.6 Subject to Section 24.3 above, the Requesting Customer may
construct their own interconnect facilities at their sole
expense; provided, however, such interconnecting facilities
shall meet all of Gulf South's technical and engineering
requirements. These interconnect facilities shall be built to
Gulf South's pipeline but only Gulf South shall construct the
tap, at the Requesting Customer's sole cost, to complete the
interconnect.