The releasing shipper may request a later posting time for posting
of such offer insofar as such request comports with the standard
Capacity Release timeline specified in GISB Standard No. 5.3.2.
TSP's nightly processing and routine maintenance occurring outside
of normal business hours are apt to interrupt the normal schedule
of applicable validation documents. Such delays should be kept to
a minimum. The normal schedule should be resumed at the earliest
opportunity and no later than the start of the next business day.
5.3.34 Transportation Service Providers should provide affected parties
with notification of intraday bumps, operational flow orders and
other critical notices through the affected party's choice of
Electronic Notice Delivery mechanism(s).
5.3.35 Unless the affected party and the Transportation Service Provider
(TSP) have agreed to exclusive notification via EDI/EDM, the
affected party should provide the TSP with at least one Internet
E-mail address to be used for Electronic Notice Delivery of
intraday bumps, operational flow orders and other critical
notices. The obligation of the TSP to provide notification is
waived until the above requirement has been met.
5.3.36 Transportation Service Providers should support the concurrent
sending of electronic notification of intraday bumps, operational
flow orders and other critical notices to two Internet E-mail
addresses for each affected party.