Gulf South Pipeline Company L P
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2003, Docket: RP03-413-000, Status: Effective
Second Revised Sheet No. 2439 Second Revised Sheet No. 2439 : Effective
Superseding: First Revised Sheet No. 2439
GENERAL TERMS AND CONDITIONS
Section 17
(Continued)
4.3.81 For a GISB FF/EDM flat file, the first row of the file should be
comprised of the standard abbreviations for GISB data elements,
including any additional data elements added per GISB Standard No.
4.3.52, in the order in which the corresponding data is to appear
in all subsequent rows. The data element order is at the option of
the sender. If a data element abbreviation is not recognized, the
entire flat file should be rejected.
4.3.82 For GISB FF/EDM flat files, each transaction (e.g. nomination)
should be contained in a single row.
4.3.83 For Interactive Flat File EDM, 128-bit Secure Sockets Layer (SSL)
encryption should be used.
4.3.84 Access to Interactive Flat File EDM should be protected by HTTP
Basic Authentication.
4.3.85 The sub-categories and the labels for the category of Capacity
Release should appear, if applicable, in the Navigational Area as
follows:
Offers
Bids
Awards
Links supporting Mutually Agreeable sub-categories will follow
these links. This does not preclude a further breakdown of sub-
sub-categories within each sub-category from being listed in the
Navigational Area.
4.3.86 To the extent that multiple electronic delivery mechanisms are
used, the same business result should occur.