Gulf South Pipeline Company L P
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2002, Docket: RP02-421-000, Status: Effective
Original Sheet No. 2415D Original Sheet No. 2415D : Effective
GENERAL TERMS AND CONDITIONS
Section 17
(Continued)
1.3.76 With respect to Title Transfer Tracking activity, when a reduction
on a party's delivery side occurs at a location, and the
Transportation Service Provider (TSP) does not keep the party
whole, the TSP should pass the reduction to the appropriately
ranked receipt transaction. When a reduction on a party's receipt
side occurs at a location, and the TSP does not keep the party
whole, the TSP should pass the reduction to the appropriately
ranked delivery transaction.
1.3.77 Where a Transportation Service Provider (TSP) determines to employ
the confirmation process in its interactions with a Title Transfer
Tracking Service Provider (TTTSP) including a TTTSP acting as the
TSP's agent, if any, then the TSP should also offer to employ with
similarly situated TTTSPs, and may at its discretion require that
other TTTSPs employ, the confirmation process in addition to the
nomination on behalf of process for the purpose of coordinating
activities at the TSP's locations with respect to Title Transfer
Tracking.
1.3.78 The effective date for implementation of the TTT standards is the
later of June 2000 or eight months following the publication of
the TTT standards within the applicable GISB standards manual.
1.3.79 On the Scheduled Quantity Web page, a mechanism should exist to
allow the display of those line items that result in nomination
reductions before all other line items are displayed, or to allow