9. OVERRUN PROVISION
If any Customer takes gas from Gulf South in excess of its contract
MDQ, such Customer shall pay Gulf South an amount equal to the product
of the Overrun Quantity times the Overrun Rate. Gulf South shall
determine Overrun Quantity based upon the difference between (1) the
total monthly allocated delivery quantities under the Customer's
contract pursuant to Section 12 hereof and (2) the product of the
contract MDQ multiplied by the number of the days in the billing month.
The "Overrun Rate" shall be the maximum applicable tariff rate,
calculated on a 100% load factor basis unless another rate is agreed to
by the parties in writing prior to the time the overrun occurs. Gulf
South will respond to a discounted overrun rate request within two (2)
hours of Customer's request. If an overrun occurs during a Critical
Period, OFO, and/or SMP, then the overrun shall be subject to the
penalties set forth in Section 19 and such other provisions of this
Tariff as may be applicable.