15.3 If Shipper's title or right to deliver Gas to be
transported is questioned or involved in any action,
Shipper shall not qualify for or shall be ineligible to
continue to receive service until such time as
Shipper's title or right to deliver is free from
question; provided, however, Transporter shall allow
Shipper to qualify for or continue receiving service
under this Tariff if Shipper furnishes a bond
satisfactory to Transporter.
15.4 Title to the Gas received by Transporter at the Receipt
Point shall not pass to Transporter.
16. FORCE MAJEURE
16.1 If either Transporter or Shipper fails to perform any
obligations under the Tariff due to an event of Force
Majeure as defined in Section 1.14, such failure shall be
deemed not to be a breach of such obligations and neither
party shall be liable in damages or otherwise as a result of
an event of Farce Majeure. A party that fails to perform any
obligations under the Tariff where such failure is caused by
an event of Force Majeure shall promptly remedy the cause of
the Force Majeure insofar as it is reasonably able to do so.
16.2 Notwithstanding the above provisions, no event of Force
Majeure shall:
(a) Relieve any party from any obligation or
obligations pursuant to the Tariff unless such
party gives notice with reasonable promptness of
such event to the other party;
(b) Relieve any party from any obligation or
obligations pursuant to the Tariff after the
expiration of a reasonable period of time within
which, by the use of its due diligence, such party
could have remedied or overcome the consequences
of such event of Force Majeure; or
(c) Relieve either party from its obligations to make
payments of amounts as provided in the applicable
Rate Schedule, subject to any credit provided for
in the applicable Rate Schedule.
16.3 In the event of a Force Majeure, Transporter shall
curtail delivery of Gas to Shipper in accordance with
section 6 hereof.