15.3 If Shipper's title or right to deliver Gas to be

transported is questioned or involved in any action,

Shipper shall not qualify for or shall be ineligible to

continue to receive service until such time as

Shipper's title or right to deliver is free from

question; provided, however, Transporter shall allow

Shipper to qualify for or continue receiving service

under this Tariff if Shipper furnishes a bond

satisfactory to Transporter.

 

15.4 Title to the Gas received by Transporter at the Receipt

Point shall not pass to Transporter.

 

16. FORCE MAJEURE

 

16.1 If either Transporter or Shipper fails to perform any

obligations under the Tariff due to an event of Force

Majeure as defined in Section 1.14, such failure shall be

deemed not to be a breach of such obligations and neither

party shall be liable in damages or otherwise as a result of

an event of Farce Majeure. A party that fails to perform any

obligations under the Tariff where such failure is caused by

an event of Force Majeure shall promptly remedy the cause of

the Force Majeure insofar as it is reasonably able to do so.

 

16.2 Notwithstanding the above provisions, no event of Force

Majeure shall:

(a) Relieve any party from any obligation or

obligations pursuant to the Tariff unless such

party gives notice with reasonable promptness of

such event to the other party;

 

(b) Relieve any party from any obligation or

obligations pursuant to the Tariff after the

expiration of a reasonable period of time within

which, by the use of its due diligence, such party

could have remedied or overcome the consequences

of such event of Force Majeure; or

 

(c) Relieve either party from its obligations to make

payments of amounts as provided in the applicable

Rate Schedule, subject to any credit provided for

in the applicable Rate Schedule.

 

16.3 In the event of a Force Majeure, Transporter shall

curtail delivery of Gas to Shipper in accordance with

section 6 hereof.