33. RESERVATION OF CAPACITY FOR EXPANSION PROJECTS (Continued)

 

If capacity that is reserved for an expansion project is insufficient

to fully meet the needs of expansion shippers, the expansion open

season posting will include a non-binding solicitation for turnback

capacity from Transporter's existing Shippers to serve the expansion

project. Transporter shall post, in the Informational Postings section

of its Internet website, a non-binding solicitation for expansion

project related turnback capacity no later than ninety (90) days after

the close of an expansion project's open season specifying the minimum

term for a response to the solicitation.

 

Any capacity reserved for a project that does not go forward for any

reason shall be reposted as generally available within thirty (30) days

of the date the capacity becomes available.