Tuscarora Gas Transmission Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/01/2009, Docket: RP09-08-000, Status: Effective

Original Sheet No. 85 Original Sheet No. 85

 

GENERAL TERMS AND CONDITIONS

 

4. NOMINATIONS, ALLOCATION OF CAPACITY AND POOLING (continued)

 

4.1 Nominations. (continued)

 

(i) Nomination Cycles (continued)

 

Scheduled quantities resulting from an Evening Nomination

that does not cause another Service Requester on the subject

Transportation Service Provider to receive notice that it is

being bumped should be effective at 9:00 A.M. (7:00 A.M. PCT)

on gas day; and when an Evening Nomination causes another

Service Requester on the subject Transportation Service

Provider to receive notice that it is being bumped, the

schedule quantities should be effective at 9:00 A.M.

(7:00 A.M. PCT) on gas day.

 

 

(3) The Intraday 1 Nomination Cycle: 10:00 am (8:00 am PCT) for

nominations leaving control of the nominating party; 10:15 am

(8:15 am PCT) for receipt of nominations by the transporter

(including from TTTSPs); 10:30 am (8:30 am) to send Quick

Response; 1:00 pm (11:00 am PCT) for receipt of completed

confirmations by transporter from upstream and downstream

connected parties; 2:00 pm (12:00 pm PCT) for Transportation

Service Provider to provide scheduled quantities to affected

shippers and point operators, and to provide scheduled

quantities to bump parties (notice to bumped parties),

(central clock time on the gas day). Scheduled quantities

resulting from Intraday 1 Nominations should be effective at

5:00 pm (3:00 pm PCT) on gas day.

 

 

(4) The Intraday 2 Nomination Cycle: 5:00 pm (3:00 pm PCT) for

nominations leaving control of the nominating party; 5:15 pm

(3:15 pm PCT) for receipt of nominations by the transporter

(including from TTTSPs); 5:30 pm (3:30 pm PCT) to send Quick

Response; 8:00 pm (6:00 pm PCT)for receipt of completed

confirmations by transporter from upstream and downstream

connected parties; 9:00 pm (7:00 pm PCT) for Transportation

Service Provider to provide scheduled quantities to affected

shippers and point operators (central clock time on the gas

day). Scheduled quantities resulting from Intraday 2

Nominations should be effective at 9:00 pm (7:00 pm PCT) on

gas day. Bumping is not allowed during the Intraday 2

Nomination Cycle.