GENERAL TERMS AND CONDITIONS
2. DEFINITION OF TERMS (continued)
2.29 Measurement Variance Gas Factor(MVGF). (continued)
Linepack Change = The change which occurred during the Measurement
Month in linepack gas contained within
Transporter's System, including changes due to
company use of gas for fuel or otherwise but
excluding any changes due to sales and purchases
of gas pursuant to Section 35 of these General
Terms and Conditions.
Prior Account = Any measurement variance gas which has been over
or under collected during the month prior to the
Measurement Month.
Forecasted Receipts
For The Applicable
Month = The forecasted receipts for the month in
which the measurement variance will be
applied.
A positive Measurement Variance Gas Factor represents a loss in
Transporter's Measurement Variance Gas. A negative Measurement
Variance Gas Factor represents a gain in Transporter's
Measurement Variance Gas.
2.30 Fuel Reimbursement.
(a) [NAESB WGQ Standard 1.3.16] Where fuel reimbursement is in
kind, the standard fuel calculation mechanism, as this is
related to the nomination process, should be (1-fuel%/100)
multiplied by receipt quantity = delivery quantity.
(b) [NAESB WGQ Standard 1.3.28] For current in-kind fuel
reimbursement procedures, fuel rates should be made effective
only at the beginning of the month.
2.31 Nomination [NAESB WGQ Standard 1.2.1]. The level of information
required to define a nomination for communications purposes is a
line item containing all defined components.
2.32 Intra-Day Nomination [NAESB WGQ Standard 1.2.4]. The term
"intra-day nomination" is a nomination submitted after the
nomination deadline whose effective time is no earlier than the
beginning of the gas day and runs through the end of that gas
day.
2.33 Data Elements [NAESB WGQ Standard 1.2.2]. All trading partners
should accept all NAESB standard data elements. Usage should be
characterized as either mandatory, conditional, sender's option,
business conditional, and mutually agreeable.