Tuscarora Gas Transmission Company

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/02/1998, Docket: RP98-428-000, Status: Effective

First Revised Sheet No. 42A First Revised Sheet No. 42A : Effective

Superseding: Original Sheet No. 42A

 

 

GENERAL TERMS AND CONDITIONS

 

(f) Receiver of nomination initiates confirmation process. The party

that would receive a Request For Confirmation or an unsolicited

Confirmation Response may waive the obligation of the sender to

send.

 

(g) The sending party should adhere to nomination, confirmation, and

scheduling deadlines. It is the party receiving the request who

has the right to waive the deadline.

 

(h) (i) With respect to the timely nomination/confirmation process at

a receipt or delivery point, in the absence of agreement to the

contrary, the lesser of the confirmation quantities should be the

confirmed quantity. If there is no responses to a Request For

Confirmation or an unsolicited Confirmation Response, the lesser

of the confirmation quantity or the previously scheduled quantity

should be the new confirmed quantity.

 

(ii) With respect to the processing of requests for increases

during the intraday nomination/confirmation process, in the

absence of agreement to the contrary, the lesser of the

confirmation quantities should be the new confirmed quantity. If

there is no response to a Request For Confirmation or an

unsolicited Confirmation Response, the previously scheduled

quantity should be the new confirmed quantity.

 

(iii) With respect to the processing of requests for decreases

during the intraday nomination/confirmation process, in the

absence of agreement to the contrary, the lesser of the

confirmation quantities should be the new confirmed quantity, but

in any event no less that the elapsed-prorated-scheduled quantity.

If there is no response to a Request for Confirmation or an

unsolicited Confirmation Response, the greater of the confirmation

quantity or the elapsed-prorated-scheduled quantity should be the

new confirmed quantity.

 

(iv) With respect to 4.1 (h) i, ii, and iii, if there is no

response to a request for confirmation or an unsolicited

confirmation response, the Transportation Service Provider should

provide the Service Requester with the following information to

explain why the nomination failed, as applicable:

(1) the Service Requester's Transportation Service Provider did

not conduct the confirmation;

(2) the Service Requester is told by its Transportation Service

Provider that the upstream confirming party did not conduct

the confirmation;

(3) the Service Requester is told by its Transportation Service

Provider that the upstream Service Requester did not have the

gas or submit the nomination;