28. MISCELLANEOUS (Continued)
28.8 Transactions utilizing the following specific receipt and delivery
point combinations shall only be subject to a lost and unaccounted
for fuel charge as prescribed by Section 22.3 of these General
Terms and Conditions.
(A) LNG Lateral
(1) Point of Receipt
At the point of interconnect between Trunkline and
Trunkline LNG Company, LLC located in Calcasieu Parish,
Louisiana.
(2) Point(s) of Delivery
All Points of Delivery on Trunkline's LNG lateral which
consists of 45.8 miles of 30-inch pipeline beginning at
the interconnection with Trunkline LNG Company, LLC and
continuing to the inlet side of Trunkline's Longville,