Trunkline Gas Company, LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2003, Docket: RP03-534-000, Status: Effective
Original Sheet No. 314 Original Sheet No. 314 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
27. TRANSITION COSTS (Continued)
(a) Trunkline's total obligations to ANR
Pipeline Company from September 1, 1993
through June 24, 1994 for service
originally certificated by the Commission
in Docket No. CP85-329, which commencing
November 1, 1992 was included in ANR's
Rate Schedule FTS at such rates as are in
effect for this service during the said
time; and
(b) Trunkline's total obligations to Stingray
Pipeline Company from September 1, 1993
through December 1, 1994 for service
certificated by the Commission in Docket
No. CP73-27 reflected in Stingray's Rate
Schedule T-1 at such rates as are in
effect for this service during the said
time.
(ii) "Initial Stranded Transportation Cost
Reservation Surcharge" or "IST Reservation
Surcharge" shall mean the currently effective
fixed monthly charge per Dt as shown on each
of Tariff Sheet Nos. 10, 12 and 13 of Third
Revised Volume No. 1.
(iii) "Initial Stranded Transportation Cost
Volumetric Surcharge" or "IST Volumetric
Surcharge" shall mean the currently effective
charge per Dt of service provided as shown on
Tariff Sheet Nos. 11 and 16 of Third Revised
Volume No. 1.
(iv) "Initial Stranded Transportation Cost
Surcharges" or "IST Surcharges" shall mean IST
Reservation Surcharges, or IST Volumetric
Surcharges, or both, as indicated by the
context.