Trunkline Gas Company, LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2003, Docket: RP03-534-000, Status: Effective
Origianl Sheet No. 226 Origianl Sheet No. 226 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
3. NOMINATION AND SCHEDULING OF SERVICES (Continued)
(D) Authorized Withdrawal Overrun Quantities
Upon request of Shipper, Trunkline may, but is not obligated
to, withdraw on any Gas Day Quantities of Natural Gas in
excess of Shipper's MDWQ under the Rate Schedule NNS-1,
NNS-2, FSS or ISS Service Agreement when, in Trunkline's sole
judgment, the capacity of its system will permit such
withdrawal, without impairing the ability of Trunkline to
meet its other obligations.
(E) The Quantities nominated by Shipper for injection into or
withdrawal from storage and Quantities injected into or
withdrawn from storage by Trunkline on behalf of Shipper
under Rate Schedule NNS-1 or NNS-2 shall be scheduled in the
following order:
(1) Firm service under Rate Schedule FSS, NNS-1 or NNS-2;
(2) Interruptible service in sequence starting with the
highest rate;
(3) Authorized Overrun Withdrawal and Injection Quantities
shall be scheduled as interruptible.
In the event a tie for capacity exists among Shippers,
Shipper's Storage Service Agreement request date will determine
the scheduling priority. For Shippers with the same request
date, Quantities shall be scheduled on a pro rata basis.
3.4 Scheduling Procedure for Parking Service
The Quantities nominated into interruptible parking service under
Rate Schedule GPS shall be scheduled in sequence starting with the
highest daily Parking rate. In the event of a tie, Quantities
will be scheduled on a pro rata basis.