Transwestern Pipeline Company, LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/23/2006, Docket: RP06-604-000, Status: Effective
First Revised Sheet No. 106 First Revised Sheet No. 106 : Effective
Superseding: Original Sheet No. 106
GENERAL TERMS AND CONDITIONS
(continued)
4.6 Deviation of the natural gas from Boyle's and Charles' Laws shall be calculated as per AGA Par
Research Project NX-19 or by AGA Transmission Measurement Committee Report No. 8, as may be
amended from time to time. The gas analysis required by Section 4.5 above shall be used for
the chemical composition of the gas as required for calculation by NX-19 or AGA-8.
5. MEASURING STATIONS
5.1 Measuring Station:
A. Measurement facilities installed and operated hereunder shall include standard orifice
meters, turbine or standard displacement meters, or any other method mutually agreed upon
by the interconnecting parties, and other necessary measuring equipment by which the
quantity of gas hereunder shall be measured. The measurement facilities, including all