28. NOMINATIONS; ALLOCATION OF CAPACITY; CURTAILMENT OF SERVICE; AND CONFIRMATIONS (Continued)
28.1 (a) (vii) All nominations should be considered original nominations and should be
replaced to be changed. An original nomination shall apply to each cycle
within the gas day unless the nomination is revised. In that event, the
revised nomination shall apply to subsequent cycles within the gas day.
Intra-day nominations can be used to request increases or decreases in
total flow, changes to receipt points, or changes to delivery points of
scheduled gas. When a nomination for a date range is received, each day
within that range is considered an original nomination. When a subsequent
nomination is received for one or more days within that range, the
previous nomination is superseded by the subsequent nomination only to the
extent of the days specified. The days of the previous nomination outside
the range of the subsequent nomination are unaffected. Nominations have a
prospective effect only.
All nominations for storage or transportation service must be made
electronically through 1Line or by electronic data interchange. However,
in the event of a failure of electronic nomination communication
equipment, Internet, or third party service provider, or other similar
emergency event which constitutes an event of force majeure pursuant to
Section 11.1 of these General Terms and Conditions, Buyer may submit and
Seller will accept written nominations, provided that such force majeure
events are documented by an affidavit provided by Buyer to Seller within
24 hours of such event. Any such requests by Buyer for emergency
treatment shall be handled on a not unduly discriminatory basis.
(b) Buyer's nomination and schedule ranks, to be deemed timely, must conform to the
following timeline (the nomination timeline shall be Central Clock Time on the
day prior to gas flow):
11:30 a.m. Electronic nomination leaves control of the Buyer for nominations
submitted by either 1Line or electronic data interchange
11:45 a.m. Receipt of nomination by Seller through electronic data
interchange, including from Title Transfer Tracking Service
Providers (TTTSPs)
12:00 p.m. Quick response by Seller regarding validity of data elements of
nominations received through electronic data interchange
3:30 p.m. Receipt of completed confirmations by Seller from upstream and
downstream connected operating entities
4:30 p.m. Scheduled quantities made available by Seller for receipt by
Shipper and point operator
(c) Buyer's nomination and schedule ranks for intraday cycles will conform to the
following timelines.
(i) Seller will accept nominations and schedule ranks for a gas day which are
received after the timely nomination and ranking deadlines identified in
Section 28.1(b) until 6:00 p.m. Central Clock Time the day before gas
flows (Evening Nomination).
Evening Nomination Cycle:
6:00 p.m. Electronic nomination leaves control of the Buyer for
nominations submitted by either 1Line or electronic data
interchange
6:15 p.m. Receipt of nomination by Seller through electronic data
interchange, including from TTTSPs
6:30 p.m. Quick response by Seller regarding validity of data elements