Transcontinental Gas Pipe Line Company, LLC
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/30/2009, Docket: RP09-793-000, Status: Effective
First Revised Sheet No. 378 First Revised Sheet No. 378
Superseding: Original Sheet No. 378
GENERAL TERMS AND CONDITIONS
(Continued)
ZONE 4
------
DAILY FACILITY GROUP AND DELIVERY POINT ENTITLEMENTS
----------------------------------------------------
ALABAMA GAS CORPORATION
--------------------------------------------
Quantities In MMCF/D @ 14.7 PSIA
-------------------------------------------------
Winter Period (1) Summer Period (2)
Facility ---------------------- ----------------------
Group Delivery Facility Delivery Facility
Geograph- Point Group Point Group
ical Maximum Maximum Maximum Maximum
Area Delivery Points DPE DPE DPE DPE
--------- ------------------- -------- -------- -------- ---------
4 Linden 2 - 2 -
Thomaston 1 - 1 -
Selma 40 (4) - 40 (4) -
--- --- --- ---
Total - 43 - 43
5 Montgomery 100 (4) - 100 (4) -
Birmingham 100 (4) - 100 (4) -
Clanton 4 - 4 -
--- --- --- ---
Total - 104 - 104
Total Firm Contract 98.0 (3,4) 98.0 (3,4)
Notes:
(1) Winter Period is October through April.
(2) Summer Period is May through September.
(3) Includes presently authorized firm service under Rate Schedule FT. Available firm
quantities limited to individual rate schedule provisions.
(4) Includes 21.256 MMCF/D delivered for Southern Company Services, Inc under Rate Schedule FT.