RATE SCHEDULE FTN

Firm Transportation Notice Service

(Continued)

 

 

 

3. RATES AND CHARGES (Continued)

 

3.9 Buyer shall reimburse Seller for the costs of any facilities installed by Seller with

Buyer's consent which are necessary to receive, measure, transport or deliver gas to or

for the account of Buyer.

 

3.10 To the extent that Buyer elects to use this rate schedule to transport withdrawal

quantities from Seller's Washington Storage Field, the following commodity charges

shall apply:

 

(a) For deliveries downstream of Zone 3 - transportation charges commence in Zone 4

and end in the zone of delivery.

 

(b) For deliveries upstream of Zone 3 - transportation charges commence in Zone 2 and

end in the zone of delivery.

 

(c) For deliveries in Zone 3 - see effective Sheet No. 38 of Volume No. 1 of this

tariff.

 

4. RECEIPTS AND DELIVERIES

 

4.1 Transportation service under this rate schedule shall consist of: (a) the receipt of

gas on behalf of Buyer up to Buyer's TCQ quantity (plus fuel retained pursuant to the

provisions of Section 3.7 hereof and injection fuel under Seller's Rate Schedule GSS,

if applicable) at (i) the point(s) of receipt specified in the executed service

agreement or (ii) at secondary point(s) of receipt pursuant to Section 2.5 hereof; (b)

the transportation of gas through Seller's pipeline; (c) the delivery of equivalent

quantities (dts) of natural gas (less fuel retained pursuant to provisions of Section

3.7 hereof) by Seller to Buyer, or for Buyer's account, at (i) the point(s) of delivery

specified in the executed service agreement, or (ii) secondary delivery points pursuant

to Section 2.5 of this rate schedule.

 

4.2 Buyer shall make any necessary arrangements with other parties so as to be able to

deliver gas to Seller at the point(s) of receipt and receive gas at the point(s) of

delivery where Seller delivers gas after transportation; provided, however, that such

arrangements shall be compatible with the operating conditions of Seller's pipeline

system and shall provide for coordinated scheduling with Seller. Buyer shall deliver,

or cause to be delivered to Seller, and Buyer shall take from Seller, the scheduled

daily quantities hereunder at uniform hourly rates.

 

4.3 Seller's ability to receive gas under this rate schedule at specific point(s) of

receipt is subject to the operating limitations of Seller and the upstream party at

such point(s) and to the availability of capacity after performance by Seller of any

existing certificated firm service arrangements under other rate schedules between

Seller and third parties at such point(s) of receipt. If an allocation of capacity at

a point of receipt is required by Seller, Seller shall prorate quantities scheduled at

that point among all Buyers under this rate schedule requesting service on that day

based upon the relative priority of scheduled quantities at the specific point(s) of

receipt on Seller's pipeline system. Quantities nominated from secondary receipt

points provided in Section 2.5 hereof, shall be interrupted first under this rate

schedule, and shall be reduced prorata based upon the requested quantities. All other

quantities scheduled hereunder will be reduced based upon relative TCQ quantities on

that segment of Seller's pipeline system.