Transcontinental Gas Pipe Line Company, LLC

Fourth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 02/22/2009, Docket: RP09-245-000, Status: Effective

First Revised Sheet No. 279 First Revised Sheet No. 279

Superseding: Original Sheet No. 279

 

RATE SCHEDULE FTN

Firm Transportation Notice Service

(Continued)

 

 

3. RATES AND CHARGES (Continued)

 

3.3 If, under the provisions of Section 11.1 through 11.4 of the General Terms and

Conditions, Seller orders interruption or reduction of service to Buyer, then the

Reservation Charge for the month in which such day or days occur shall be computed as

follows: Determine for each such day the number of dt which Seller was unable to

deliver, and multiply the sum of all such days' deficiencies by the reservation rate

per dt of TCQ, and the result shall be subtracted from the Reservation Charge for such

month as otherwise computed. No adjustment to the Reservation Charge shall be made as

a result of a reduction or interruption of service under the provisions of Sections

11.5 and 11.6 of the General Terms and Conditions.

 

3.4 For transportation service under this rate schedule, the Commodity Charge shall

consist of the applicable FTN commodity rate multiplied by the quantities (dt)

delivered.

 

3.5 The maximum and minimum reservation and commodity rates for firm transportation

service are shown on the effective Sheet Nos. 37 and 38 of Volume No. 1 of this

Tariff. Buyer shall pay such maximum rates for service under this rate schedule

unless Seller, in its sole judgment, agrees to discount its rate to Buyer. Such

discount may be granted consistent with the applicable provisions of Section 40 of the

General Terms and Conditions. Further, Buyer and Seller may mutually agree to a

negotiated rate pursuant to the provisions of Section 53 of the General Terms and

Conditions. Such negotiated rate shall be set forth in the executed Service

Agreement.

 

3.6 For purposes of capacity release, the Reservation Charges per TCQ payable by Buyer

shall be as set forth in the applicable capacity release award posted on 1Line

consistent with the provisions of Section 42 of the General Terms and Conditions. The

maximum reservation rates for firm transportation service are shown on the effective

Sheet No. 37 of Volume No. 1 of this Tariff, however, for releases that become

effective on or after July 30, 2008, the maximum rate ceiling does not apply to such

releases provided the release is for a term of one year or less and the release is to

take effect on or before one year from the date on which the pipeline is notified of

the release. The rate paid in any capacity release transaction not subject to the

maximum rate ceiling will not be subject to refund. The minimum reservation rate

applicable to capacity release transactions that are not permanent releases shall be

zero unless otherwise specified in the capacity release offer. The maximum and

minimum commodity rates for firm transportation service are shown on the effective

Sheet No. 38 of Volume No. 1 of this tariff.

 

3.7 Seller shall retain from the quantities of gas delivered by Buyer at the point(s) of

receipt for transportation under this rate schedule a percentage(s) of such gas for

compressor fuel and line loss make-up. Such percentage(s) are specified on the

effective Sheet No. 81 of Volume No. 1 of this Tariff.

 

3.8 Buyer shall pay Seller any and all filing fees incurred as a result of Buyer's request

for Seller's performance of service under this rate schedule, to the extent such fees

are imposed upon Seller by the FERC or any other governmental authority having

jurisdiction. Buyer shall pay Seller for such fees at Seller's designated office or

depository within ten days of receipt of Seller's invoice detailing the amount of such

fees.