RATE SCHEDULE FT-G
FIRM TRANSPORTATION SERVICE
(Continued)
2. APPLICABILITY AND CHARACTER OF SERVICE (Continued)
2.9 For transportation service under this Rate Schedule the following terms shall apply in
order to indicate direction of flow:
(a) Primary Path
The transportation path established by the receipt and delivery points as set
forth in Buyer's executed Service Agreement.
(b) Reverse Path
The transportation path that is in the opposite direction of the Primary Path as
defined in Section 2.9(a) above.
3. RATES AND CHARGES
3.1 For transportation service rendered to Buyer under this Rate Schedule, Buyer shall pay
to Seller the applicable rate multiplied by the quantities (dts) delivered.
3.2 RESERVED FOR FUTURE USE.
3.3 The maximum and minimum unit rates for FT-G transportation service are shown on the
effective Sheet No. 39 of Volume No. 1 of this tariff. Buyer shall pay such maximum
rates for service under this Rate Schedule unless Seller, in its sole judgment, agrees
to discount its rate to Buyer. Such discount may be granted consistent with the
applicable provisions of Section 40 of the General Terms and Conditions. Further,
Buyer and Seller may mutually agree to a negotiated rate pursuant to the provisions of
Section 53 of the General Terms and Conditions. Such negotiated rate shall be set
forth in the executed Service Agreement.
3.4 Seller shall retain from the quantities of gas delivered by Buyer at the point(s) of
receipt for transportation under this Rate Schedule a percentage(s) of such gas for
compressor fuel and line loss make-up. Such percentage(s) are specified on the
effective Sheet No. 81 of Volume No. 1 of this Tariff.
3.5 Buyer shall pay Seller any and all filing fees incurred as a result of Buyer's request
for Seller's performance of service under this Rate Schedule, to the extent such fees
are imposed upon Seller by the FERC or any other governmental authority having
jurisdiction. Buyer shall pay Seller for such fees at Seller's designated office or
depository within ten days of receipt of Seller's invoice detailing the amount of such
fees.
3.6 Buyer shall reimburse Seller for the costs of any facilities installed by Seller with
Buyer's consent which are necessary to receive, measure, transport or deliver gas to
or for the account of Buyer.
3.7 To the extent that Buyer elects to utilize this Rate Schedule to transport withdrawal
quantities from Seller's Washington Storage Field, the following charges shall apply:
(a) For deliveries downstream of Zone 3 - transportation charges commence in Zone 4
and end in the zone of delivery.
(b) For deliveries upstream of Zone 3 - transportation charges commence in Zone 2 and
end in the zone of delivery.