Transcontinental Gas Pipe Line Company, LLC
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/31/2008, Docket: RP09-158-000, Status: Effective
Original Sheet No. 181 Original Sheet No. 181
RATE SCHEDULE FT
Firm Transportation Service
(Continued)
3. RATES AND CHARGES
3.1 For transportation service rendered to Buyer each month under this Rate Schedule,
Buyer shall pay to Seller the sum of Seller's Reservation and Commodity Charge(s)
determined as follows:
(a) Reservation Charge: Buyer's applicable TCQ(s) multiplied by the applicable
reservation rate(s) multiplied by the number of days in the
month that capacity was held. If Buyer acquires capacity
through a volumetric release, the reservation charge shall
be the rate set forth in the applicable capacity release
award posted on 1Line multiplied by the quantities (dts)
delivered each day (up to Buyer's TCQ); provided, however,
Buyer's monthly bill may be subject to adjustment to
account for any minimum volumetric commitment specified in
such capacity release award.
(b) Commodity Charge: The applicable FT commodity rate(s) multiplied by the
quantities (dts) delivered.
3.2 For transportation service under this Rate Schedule, Seller's Reservation Charges
shall be calculated as follows:
(a) The Reservation Charge each month for a Conversion Buyer (as defined in Section 7
of this Rate Schedule) shall be determined as the sum of the following:
(i) 17% x Buyer's TCQ x the applicable reservation rate from Zone 1
(Station 30) to Buyer's delivery zone x the number of
days in the month that capacity was held.
(ii) 25% x Buyer's TCQ x the applicable reservation rate from Zone 2
(Station 45) to Buyer's delivery zone x the number of
days in the month that capacity was held.
(iii) 19% x Buyer's TCQ x the applicable reservation rate from Zone 3
(Station 50) to Buyer's delivery zone x the number of
days in the month that capacity was held.
(iv) 39% x Buyer's TCQ x the applicable reservation rate from Zone 3
(Station 62) to Buyer's delivery zone x the number of
days in the month that capacity was held.
(b) In addition to the above, Conversion Buyers electing firm capacity entitlements
described in Section 7.4 of this Rate Schedule shall pay a Reservation Charge
each month under this Rate Schedule determined by multiplying Buyer's TCQ
attributable to the firm capacity so elected by the Zone 3-3 Reservation Rate for
each day in the month that capacity was held.
(c) The Reservation Charge each month for all other Buyers under this Rate Schedule
shall be determined by multiplying Buyer's TCQ by the applicable reservation rate
for each day in the month that capacity was held.