Transcontinental Gas Pipe Line Company, LLC

Fourth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/01/2009, Docket: RP09-971-000, Status: Effective

First Revised Sheet No. 119 First Revised Sheet No. 119

Superseding: Original Sheet No. 119

 

RATE SCHEDULE S-2

Storage Service

Zone 6

 

 

1. AVAILABILITY

 

This rate schedule is available for the purchase of storage service from Transcontinental Gas

Pipe Line Company, LLC (hereinafter referred to as Seller) by Public Service Electric and Gas

Company, PECO Energy Company, The Brooklyn Union Gas Company, Pivotal Utility Holdings, Inc.,

South Jersey Gas Company and Philadelphia Gas Works (each hereinafter referred to as Buyer)

provided Buyer has executed a service agreement with Seller for service under this rate

schedule. The availability of storage service hereunder is contingent on and subject to the

availability of storage service provided by Texas Eastern Transmission, LP (TETCO) to Seller

under TETCO's Rate Schedule X-28.

 

2. APPLICABILITY AND CHARACTER OF SERVICE

 

This rate schedule shall apply to storage service rendered by Seller to Buyer under the

service agreement executed for service hereunder. Service rendered under this rate schedule,

within the limitations set forth in Sections 5 and 6 hereof, shall be on a firm basis and

shall not be subject to reduction or interruption, except as provided in Section 11 of the

General Terms and Conditions; provided, however, that in the event TETCO fails for any reason

whatsoever to make deliveries to Seller or receive gas from Seller under TETCO's Rate

Schedule X-28 then Seller's obligation hereunder shall be reduced accordingly.

 

3. RATES AND CHARGES

 

3.1 The applicable charges set forth in that portion of the currently effective Sheet No.

24 of Volume No. 1 of this Tariff which relates to this Rate Schedule are incorporated

herein.

 

3.2 For natural gas service rendered to Buyer under this Rate Schedule, Buyer shall pay

Seller for each day each month the sum of the following amounts:

 

(a) Demand Charge: A charge per day per dt of Contract Storage Demand.

 

(b) Storage Capacity Charge: A charge per day per dt of Storage Capacity Quantity.

 

(c) Injection Charge: A charge per dt of natural gas nominated by Buyer for

injection.

 

(d) Withdrawal Charge: A charge per dt of natural gas nominated by Buyer for

withdrawal.

 

3.3 Storage Cost Credit - Seller shall credit Buyer's invoice each month by an amount

equal to Buyer's proportionate share of the Storage Cost Credit received by Seller

from TETCO, if any. Buyer's proportionate share of the Storage Cost Credit shall be

calculated each month by multiplying Buyer's Contract Storage Demand as a percentage

of total Contract Storage Demand under this Rate Schedule times the Storage Cost

Credit received by Seller from TETCO.

 

3.4 Fuel Allowance - In order to recover quantities of fuel that TETCO retains for company

use and for calculated normal operational loss associated with the injection,

withdrawal and storage of natural gas quantities, Seller will retain equivalent

quantities of fuel from Buyer's storage injection quantities (injection allowance) and

withdrawal quantities (withdrawal allowance) and from Buyer's average daily balance of

gas stored during the month (Inventory Level Allowance). Seller's fuel retention

percentages are set forth on the currently effective Sheet No. 24 of Volume No. 1 of

this Tariff.