Transcontinental Gas Pipe Line Company, LLC
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2010, Docket: RP10-776-000, Status: Effective
Original Sheet No. 59 Original Sheet No. 59
FIRM TRANSPORTATION SERVICE RATES
UNDER RATE SCHEDULE FT APPLICABLE TO
85 NORTH EXPANSION PROJECT (85 NORTH)
FIRM TRANSPORTATION SERVICE
Incremental 85 North Annual Firm Transportation
-----------------------------------------------
Maximum Minimum
Daily Daily
Rate Rate
------- -------
($) ($)
Reservation Rate per dt - Zone 4 - 4:
Base Rate 0.21675 0.00000 1/
Electric Power Unit Rate 0.00105 0.00105
------- -------
Total Reservation Rate 0.21780 0.00105
Commodity Rate per dt: 2/ 3/
Electric
Power
Base Unit Maximum Minimum
Receipt & Delivery Zone Rate Rate Rate 4/ Rate 4/
----------------------- ------- -------- ------- -------
($) ($) ($) ($)
4-4 0.00000 0.00326 0.00326 0.00326
Footnotes:
1/ The minimum reservation rate applicable to capacity release transactions that are not
permanent releases shall not be less than zero.
2/ Pursuant to Section 27 of the General Terms and Conditions, the Commodity Rate shall be
increased to include the ACA unit rate of $ 0.00190, if applicable.
3/ The Commodity Rate applies to upstream or downstream transactions on Buyer's primary or
reverse path.
4/ The Base Rate plus the Electric Power unit rate.