Transcontinental Gas Pipe Line Company, LLC
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2010, Docket: RP10-395-000, Status: Effective
Third Revised Sheet No. 48 Third Revised Sheet No. 48
Superseding: Second Revised Sheet No. 48
FIRM TRANSPORTATION SERVICE RATES
UNDER RATE SCHEDULE FT APPLICABLE TO
SUNDANCE EXPANSION PROJECT
FIRM TRANSPORTATION SERVICE
Incremental Sundance Annual Firm Transportation
-----------------------------------------------
Maximum Minimum
Daily Daily
Rate Rate
------- -------
($) ($)
Capacity rights commencing at Station 65:
Reservation Rate per dt - Zone 3-4:
Base Rate 0.23879 0.00000 1/
Electric Power Unit Rate 0.00136 0.00136
------- -------
Total Reservation Rate 0.24015 0.00136
Reservation Rate per dt - Zone 3-5:
Base Rate 0.23879 0.00000 1/
Electric Power Unit Rate 0.00213 0.00213
------- -------
Total Reservation Rate 0.24092 0.00213
Capacity rights commencing at Destin:
Reservation Rate per dt - Zone 4-4:
Base Rate 0.23879 0.00000 1/
Electric Power Unit Rate 0.00105 0.00105
------- -------
Total Reservation Rate 0.23984 0.00105
Reservation Rate per dt - Zone 4-5:
Base Rate 0.23879 0.00000 1/
Electric Power Unit Rate 0.00182 0.00182
------- -------
Total Reservation Rate 0.24061 0.00182
Firm transportation service for specified delivery
points on the North Georgia extension:
Reservation Rate per dt - Zone 4:
Base Rate 0.38772 0.00000 1/
Electric Power Unit Rate 0.00105 0.00105
------- -------
Total Reservation Rate 0.38877 0.00105
Note:
1/ The minimum reservation rate applicable to capacity release transactions that are not
permanent releases shall not be less than zero.