Transcontinental Gas Pipe Line Company, LLC
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2010, Docket: RP10-395-000, Status: Effective
Fifth Revised Sheet No. 42 Fifth Revised Sheet No. 42
Superseding: Fourth Revised Sheet No. 42
FIRM TRANSPORTATION SERVICE RATES
UNDER RATE SCHEDULE FT APPLICABLE TO
SOUTHCOAST EXPANSION PROJECT (SOUTHCOAST)
FIRM TRANSPORTATION SERVICE
Incremental Southcoast Annual Firm Transportation
-------------------------------------------------
Maximum Minimum
Daily Daily
Reservation Rate per dt - Zone 4 Rate Rate
-------------------------------- ------- -------
($) ($)
Firm Transportation Service For Specified Mainline
Delivery Points
Base Rate 0.17439 0.00000 1/
Electric Power Unit Rate 0.00105 0.00105
------- -------
Total Reservation Rate 0.17544 0.00105
Firm Transportation Service For Specified Delivery
Points on the Georgia Extension
Base Rate 0.29435 0.00000 1/
Electric Power Unit Rate 0.00105 0.00105
------- -------
Total Reservation Rate 0.29540 0.00105
Commodity Rate per dt - Zone 4
------------------------------
Base Rate 0.00016 0.00016
Electric Power Unit Rate 0.00326 0.00326
------- -------
Total Commodity Rate (excluding ACA) 2/ 3/ 0.00342 0.00342
Notes:
1/ The minimum reservation rate applicable to capacity release transactions that are not
permanent releases shall not be less than zero.
2/ Pursuant to Section 27 of the General Terms and Conditions, the Total Commodity Rate shall
be increased to include the ACA unit rate of $0.00190, if applicable.
3/ The Total Commodity Rate applies to upstream or downstream transactions on Buyer's primary
or reverse path.