Texas Gas Transmission, LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2009, Docket: RP09-07-000, Status: Suspended
Original Sheet No. 2103A Original Sheet No. 2103A
GENERAL TERMS AND CONDITIONS
Section 9
(Cont'd)
9.2.8 Procedure for Filing (cont'd)
Texas Gas may, however, file interim proposals between annual filings
subject to approval by the Commission with at least thirty days notice.
In addition, for leased capacity from Texas Eastern Transmission, LP,
under which Texas Gas shall incur fuel charges, such fuel charges, which
shall be subject to change from time to time, will be separately stated in
Texas Gas' FERC Gas Tariff on Sheet No. 37, and recovered only from those
parties actually using the leased capacity. Further, for leased capacity
from Gulf South Pipeline Company, LP, under which Texas Gas shall incur
fuel charges, such fuel charges will be separately stated in Texas Gas'
FERC Gas Tariff on Sheet No. 38, and recovered only from those parties
actually using the leased capacity. Texas Gas will update these rates
annually or more frequently, as necessary, as its system fuel rates or
Texas Eastern Transmission, LP's fuel rates change.