Texas Gas Transmission, LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2009, Docket: RP00-426-042, Status: Effective
Original Sheet No. 90 Original Sheet No. 90
STATEMENT OF NEGOTIATED RATES
Shipper Name: Southwestern Energy Services Company (Southwestern)
Contract No.: 27437
Rate Schedule: FT
Time Period(s): April 1, 2010, and continuing for a ten (10) year term beginning on the date that the Contract Demand
increases to 240,000 MMBtu per day.
Quantity(ies): 80,000 MMBtu per day beginning April 1, 2010
160,000 MMBtu per day beginning April 1, 2011
240,000 MMBtu per day beginning April 1, 2012
Provided, however, the Contract Demand Schedule above shall be superseded and the Contract Demand shall be
240,000 MMBtu/day beginning the later of (a) April 1, 2010, or (b) the first day of the month after Texas
Gas has completed installation of compression facilities at Isola, MS.
Point(s): Eligible Primary Receipt Point(s): TETCO-Kosciusko, Meter No. 9560
Eligible Primary Delivery Point(s): Columbia Gulf-Isola, Meter No. 9519
ANR-Burdette, Meter No. 9503
Trunkline-Burdette, meter No. 9504
Tennessee-Greenville, Meter No. 9500
Tennessee-Isola, Meter No. 9505
Eligible Secondary Delivery Point(s): Columbia Gulf-Isola, Meter No. 9519
ANR-Burdette, Meter No. 9503
Trunkline-Burdette, meter No. 9504
Tennessee-Greenville, Meter No. 9500
Tennessee-Isola, Meter No. 9505
Negotiated Rate(s): The rates set forth below will remain in effect for the term of this Agreement without regard to Texas Gas' maximum
or minimum applicable rates.
This Negotiated Rate Agreement shall in no event be construed as waiving any rights that Southwestern has under the
MFN Contract (defined below) or relieving Texas Gas of its obligations to Southwestern under the MFN Contract.
$0.005 per MMBtu per day, inclusive of all demand and commodity charges within contract demand, plus applicable ACA
surcharges.
*Continued on Sheet No. 90A