Texas Gas Transmission, LLC

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/01/2009, Docket: RP00-426-042, Status: Effective

Original Sheet No. 81 Original Sheet No. 81

 

STATEMENT OF NEGOTIATED RATES

 

Shipper Name: Petrohawk Energy Corporation (Petrohawk)

Contract No.: 27432

Rate Schedule: FT

 

Time Period(s): The later of (i) January 1, 2009 or (ii) the first day of the month following the date on which the

Expansion Project facilities are complete and made available for service (the "Effective Date") through

nine (9) years from the effective date of the Firm Transportation Agreement (the "Negotiated Rate

Termination Date"). For purposes of this Agreement and Contract No. 27432, the term "Fayetteville

Expansion Project" refers to the expansion by Texas Gas of its system by the installation of a lateral

line of at least 18" in diameter from near Grandview in eastern Conway County, Arkansas and connecting

with its existing mainline system near Lula, Mississippi.

Quantity(ies): 100,000 MMBtu per day

Point(s): Eligible Primary Receipt Point(s): Boy Scout, Meter No. 9091

Big Hawk, Meter No. 9092

Quitman West, Meter No. 9093

Quitman East, Meter No. 9095

Southeast Rainbow #1, Meter No. 9027

Eligible Secondary Receipt Point(s): Other points of interconnection on the Fayetteville Lateral

Eligible Primary Delivery Point(s): Lula, Meter No. 9714

Eligible Secondary Delivery Point(s): NGPL-Bald Knob, Meter No. 9163

MRT-Bald Knob, Meter No. 9799

TETCO-Bald Knob, Meter No. 9533

 

Negotiated Rate(s): Notwithstanding anything provided in Paragraph 9 of the Firm Transportation, Contract No. 27432, the rates set for

below will remain in effect for the primary term of this Agreement without regard to Texas Gas' maximum or minimum

applicable rates.

 

Demand: $0.2000 MMBtu per day

 

Commodity: $0.0010 MMBtu plus applicable ACA surcharge

 

Fuel: 0.10% per MMBtu from the initiation of service under this agreement until Texas Gas installs compression on the

Fayetteville Lateral to effectuate deliveries to Lula, MS

 

0.65% per MMBtu beginning on the date that Texas Gas installs compression on the Fayetteville Lateral to effectuate

deliveries to Lula, MS

 

 

 

Continued on Sheet No. 81A