Texas Gas Transmission, LLC

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/01/2009, Docket: RP00-426-042, Status: Effective

Original Sheet No. 80 Original Sheet No. 80

 

STATEMENT OF NEGOTIATED RATES

 

Shipper Name: Chesapeake Energy Marketing, Inc. (Chesapeake)

Contract No.: 27587

Rate Schedule: STF

Time Period(s): The later of (i) April 1, 2009 or (ii) the first day of the month following the date on which the

Expansion Project facilities are complete and made available for service and extending through March 31,

2010.

Quantity(ies): 40,000 MMBtu per day April 1, 2009 through May 31, 2009

112,500 MMBtu per day June 1, 2009 through June 30, 2009

150,000 MMBtu per day July 1, 2009 through December 31, 2009

112,500 MMBtu per day January 1, 2010 through March 31, 2010

Point(s): Eligible Primary Receipt Point(s): Mountain Home, Meter No. 9071 (June 1, 2009 through March 31, 2010)

Twin Groves, Meter No. 9097 (June 1, 2009 through March 31, 2010)

South Rainbow, Meter No. 9020 (April 1, 2009 through May 31, 2009)

Southeast Rainbow, Meter No. 9027 (April 1, 2009 through May 31, 2009)

Cove Creek, Meter No. 9050 (April 1, 2009 through May 31, 2009)

Eligible Secondary Receipt Point(s): Other points of interconnection on the Fayetteville Lateral

Eligible Primary Delivery Point(s): Lula, Meter No. 9714

Eligible Secondary Delivery Point(s): NGPL-Bald Knob, Meter No. 9163

MRT-Bald Knob, Meter No. 9799

TETCO-Bald Knob, Meter No. 9533

Negotiated Rate(s):

Demand: $0.2000 per MMBtu per day

$0.2400 per MMBtu per day (receipts at Twin Groves, Meter No. 9097, South Rainbow, Meter No. 9020, Southeast Rainbow,

Meter No. 9027, Cove Creek, Meter No. 9050)

 

Commodity: $0.0010 per MMBtu plus applicable ACA surcharge

 

Fuel: 0.10% per MMBtu (Beginning June 1, 2009 through the earlier of (i) March 31, 2010 and (ii) the date Texas Gas

installs compression on the Fayetteville Lateral to effectuate deliveries to Lula, MS)

 

1.25% per MMBtu (Beginning the earlier of (i) April 1, 2010 and (ii) the date that Texas Gas installs compression on

the Fayetteville Lateral to effectuate deliveries to Lula, MS

 

Point Qualification(s): The Negotiated Rates shall apply to transportation service from the Eligible Primary and Secondary Receipt Points to

the Eligible Primary and Secondary Delivery Points.

 

Chesapeake shall pay Texas Gas' maximum applicable transportation and fuel rates to the extent gas is transported

using a receipt or delivery point other than the Eligible Primary and Secondary Receipt and Delivery Points listed

above.

 

Other: N/A