Texas Gas Transmission, LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2009, Docket: RP09-962-000, Status: Effective
Second Revised Sheet No. 28 Second Revised Sheet No. 28
Superseding: First Revised Sheet No. 28
Currently Effective Maximum Transportation Rates ($ per MMBtu)
For Service Under Rate Schedule SNS
Currently
Base Tariff FERC Effective
Rates ACA Rates
(1) (2) (3)
Up to 1/16 Hourly Flow:
Daily Demand:
Zone SL 0.1800 0.0000 0.1800
Zone 1 0.2782 0.0000 0.2782
Zone 2 0.3088 0.0000 0.3088
Zone 3 0.3543 0.0000 0.3543
Zone 4 0.4190 0.0000 0.4190
Commodity:
Zone SL 0.0253 0.0019 0.0272
Zone 1 0.0431 0.0019 0.0450
Zone 2 0.0460 0.0019 0.0479
Zone 3 0.0490 0.0019 0.0509
Zone 4 0.0614 0.0019 0.0633
Daily Overrun:
Zone SL 0.2053 0.0019 0.2072
Zone 1 0.3213 0.0019 0.3232
Zone 2 0.3548 0.0019 0.3567
Zone 3 0.4033 0.0019 0.4052
Zone 4 0.4804 0.0019 0.4823
Minimum Rate: Demand $-0-; Commodity - Zone SL 0.0163
Zone 1 0.0186
Zone 2 0.0223
Zone 3 0.0262
Zone 4 0.0308
Notes:
- For receipts from Enterprise Texas Pipeline, L.P./Texas Eastern Transmission, LP interconnect
near Beckville, Texas, Customer shall pay an incremental transportation charge of:
Daily Demand $0.0621
Commodity $0.0155
Overrun $0.0776
This receipt point is available to those customers agreeing to pay the incremental rate(s)
applicable to such point and is not available for pooling under Rate Schedule TAPS.
- For receipts from Duke Field Services' Carthage Plant/Gulf South Pipeline Company, LP,
Enbridge Pipelines, L.P./Gulf South Pipeline Company, LP, Energy Transfer Company/Gulf South
Pipeline Company, LP, and Enterprise Texas Pipeline L.P./Gulf South Pipeline Company, LP
interconnects in Panola County, Texas, Customer shall pay an incremental transportation charge
of:
Daily Demand $0.1288
Commodity $0.0068
Overrun $0.1356
These receipt points are available to those customers agreeing to pay the incremental rate(s)
applicable to such points and are not available for pooling under Rate Schedule TAPS.