Texas Gas Pipe Line Corporation
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1990, Docket: RP90-112-001, Status: Effective
Substitute Original Sheet No. 19 Substitute Original Sheet No. 19 : Effective
Superseding: Original Sheet No. 19
GENERAL TERMS AND CONDITIONS (Cont,d)
12. PURCHASED GAS COST ADJUSTMENT (Cont'd)
as defined by Section 154.302(j) of the Commission's
regulations and any amounts recorded for that month
for nonconcurrent exchange transactions. The Actual Cost
of Purchased Gas shall be increased or decreased, as
appropriate, to adjust for exchange transactions and
transportation imbalances in accordance with Section
154.305(j) of the Commission's regulations.
(c) In addition to the costs computed under (a) and (b)
above, the current deferral subaccount balance may include
adjustments to a prior month's actual cost of gas purchased,
transfers from the refund subaccount, transfers of
unamortized balances after the related surcharge recovery
period has expired, and carrying charges.
12.8 Seller shall determine from its Unrecovered Purchased
Gas Costs Account for each deferral period the debit or
credit balance to be recovered or returned by Surcharge
Adjustments. The Surcharge Adjustment necessary to amortize
the balance shall be computed to the nearest 1/100 cent by
dividing the amount in the current deferral subaccount by
the forecast sales under the affected rates during the
succeeding surcharge recovery period. The resulting
Surcharge Adjustment will be in effect for the applicable
surcharge recovery period. For each twelve (12) month deferral
period the surcharge recovery period shall be the succeeding
twelve (12) calendar month period commencing on the effective
date of Seller's annual Purchased Gas Adjustment filing
(November 1).
12.9 Seller shall submit to the Commission an assessment of
past performance at the same time as it submits its annual
Purchased Gas Adjustment filing, or as otherwise required by
the Commission. The assessment shall be developed, and the
amount of gas costs which require specific Commission
approval for surcharge recovery shall be determined, in
accordance with Section 154.306 of the Commission's
regulations.