Tennessee Gas Pipeline Company
FIFTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/05/2005, Docket: RP06- 10-000, Status: Effective
Fifth Revised Sheet No. 593C Fifth Revised Sheet No. 593C : Effective
Superseding: Fourth Revised Sheet No. 593C
Agreement between Tennessee Gas
Pipeline Company ("Transporter") and
___________________________ ("Third Party Provider or TPP Contractor")
dated ________________________
TPP Agreement
This Agreement is entered into between Transporter and _________________, a
Third Party Provider ("TPP") that has entered into a Balancing Agreement in the form set
forth in Transporter's FERC Gas Tariff (hereinafter referred to as "TPP Contractor").
The individual facilities owned/operated by Transporter and by TPP Contractor
interconnect at ___________________ (the "TPP Service Point") and TPP Contractor has
entered into agreements with its customers providing for the receipt and delivery of gas
by TPP Contractor at the TPP Service Point.
TPP Contractor further desires to provide for the receipt or delivery of gas at
the TPP Service Point for its customers who have elected or may elect TPP Service
pursuant to Section 8 and/or Section 9 of Transporter's LMS-MA Rate Schedule. In
recognition of this desire, TPP Contractor and Transporter further agree as follows:
1. Information - TPP Contractor must have the ability to verify changes in flow by
real time validation to Transporter through electronic telemetry equipment.
2. Confirmation of Balancing Parties - No later than 5 business days prior to the
beginning of each month, TPP Contractor shall confirm with Transporter, either
through Transporter's PASSKEY or via fax, the identities of the Balancing
Parties using TPP Contractor to provide a swing service as part of the TPP
Service pursuant to Section 8 and/or Section 9 of Transporter's LMS-MA Rate
Schedule.
3. Confirmation of Nominations - In addition to the provisions of Article I of the
Balancing Agreement, each day the Parties shall reconcile and confirm, through
Transporter's PASSKEY or via fax, the quantities of gas scheduled for receipt or
delivery at the TPP Service Point ("TPP Quantities") on a prospective basis as
well as the quantities of gas allocated to the TPP Service Point through the TPP
Service ("Swing Quantities") on a retroactive basis. Two (2) business days
after actual flow, Transporter shall provide to TPP Contractor, via PASSKEY or
fax, its best available data as to the Swing Quantities allocated to the TPP
Service Point. Upon receipt of such data, TPP Contractor shall, within one (1)
hour, commence providing for receipt or delivery of gas at the TPP Service Point
to make-up for such Swing Quantities, in addition to the normal daily receipt or
delivery of gas for TPP Quantities and complete such make-up within twenty-four
(24) hours of commencement; provided that upon notice by Transporter,
Transporter and TPP Contractor may establish a longer period of time for such
make-up if operational conditions exist that warrant the extension. Any changes
to TPP Quantities shall be effective only if agreed to by both Parties. Such
communication regarding changes shall be substantially in the form mutually
agreeable to the Parties.