Tennessee Gas Pipeline Company

FIFTH REVISED VOLUME NO. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/03/2001, Docket: RP02- 17-000, Status: Effective

Third Revised Sheet No. 511 Third Revised Sheet No. 511 : Effective

Superseding: First Revised Sheet No. 511

 

 

SERVICE REQUEST FORM (continued)

 

 

9. If additional or new facilities are required to receive or deliver gas for the

transportation or storage service requested herein, please provide description of

facilities required, location, and requested in-service date.

 

________________________________________________________________________________

 

________________________________________________________________________________

 

________________________________________________________________________________

 

10. For service pursuant to Rate Schedule FT-A, IT, FT-G, FT-GS, FT-BH or FT-IL, the

maximum daily quantity to be transported is ____________ MMBtu and

________________ Mcf. The estimated total quantity of gas to be transported

during the requested term of service is ___________MMBtu and ___________ Mcf.

 

11. For service pursuant to Rate Schedule FS or IS, the Maximum Storage Quantity to be

stored is _____ MMBtu. The Maximum Daily Withdrawal Quantity is ________.

 

12. For service pursuant to Rate Schedules FT-A, IT, FT-G, FT-GS, FT-BH or FT-IL,

provide the name and a description of Primary Receipt Point(s) into Tennessee's

system and the maximum daily quantities expressed in MMBtu and Mcf's of gas to be

delivered by Shipper for each point. (If the request is for service under a firm

transportation rate schedule then the sum of the maximum quantities above must

equal the maximum daily quantity above.)

 

________________________________________________________________________________

 

________________________________________________________________________________

 

________________________________________________________________________________

 

________________________________________________________________________________

 

 

13. For service pursuant to Rate Schedule FS and IS, designate the Service Point

(either Transporter's compressor station 313, compressor station 87, compressor

station 40, or mainline valve 121).

 

14. Name and description of Delivery Point(s) where Tennessee will redeliver the gas

and the maximum daily quantities expressed in MMBtu and Mcf's of gas to be

redelivered by Tennessee for each point:

 

________________________________________________________________________________

 

________________________________________________________________________________

 

________________________________________________________________________________

 

(If the request is for service under a firm transportation rate schedule then the

sum of the maximum quantities must equal the maximum transportation quantity in

above unless the shipper otherwise qualifies for redundant delivery point rights

under the terms of the applicable rate schedule.)