SERVICE REQUEST FORM (continued)
9. If additional or new facilities are required to receive or deliver gas for the
transportation or storage service requested herein, please provide description of
facilities required, location, and requested in-service date.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
10. For service pursuant to Rate Schedule FT-A, IT, FT-G, FT-GS, FT-BH or FT-IL, the
maximum daily quantity to be transported is ____________ MMBtu and
________________ Mcf. The estimated total quantity of gas to be transported
during the requested term of service is ___________MMBtu and ___________ Mcf.
11. For service pursuant to Rate Schedule FS or IS, the Maximum Storage Quantity to be
stored is _____ MMBtu. The Maximum Daily Withdrawal Quantity is ________.
12. For service pursuant to Rate Schedules FT-A, IT, FT-G, FT-GS, FT-BH or FT-IL,
provide the name and a description of Primary Receipt Point(s) into Tennessee's
system and the maximum daily quantities expressed in MMBtu and Mcf's of gas to be
delivered by Shipper for each point. (If the request is for service under a firm
transportation rate schedule then the sum of the maximum quantities above must
equal the maximum daily quantity above.)
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
13. For service pursuant to Rate Schedule FS and IS, designate the Service Point
(either Transporter's compressor station 313, compressor station 87, compressor
station 40, or mainline valve 121).
14. Name and description of Delivery Point(s) where Tennessee will redeliver the gas
and the maximum daily quantities expressed in MMBtu and Mcf's of gas to be
redelivered by Tennessee for each point:
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
(If the request is for service under a firm transportation rate schedule then the
sum of the maximum quantities must equal the maximum transportation quantity in
above unless the shipper otherwise qualifies for redundant delivery point rights