Tennessee Gas Pipeline Company

FIFTH REVISED VOLUME NO. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 05/01/2002, Docket: GT02- 13-000, Status: Effective

Fourth Revised Sheet No. 402 Fourth Revised Sheet No. 402 : Effective

Superseding: Third Revised Sheet No. 402

 

 

GENERAL TERMS AND CONDITIONS (continued)

 

 

2. Information Required for Storage and Transportation Service

 

Any request for Part 284 storage service must contain the following information,

in writing:

 

(a) Contractual Quantities: The quantity of service requested as the Maximum

Storage Quantity and, with respect to firm service, the quantity requested

as the Maximum Daily Withdrawal Quantity (as defined in the applicable

rate schedule).

 

(b) Term of Service: The proposed commencement and termination dates for firm

service and a termination date of at least thirty days after service

commencement for interruptible service.

 

(c) Service Point: The designated Service Point, as defined in the applicable

rate schedule, for gas to be injected into or withdrawn from storage.

 

Any request for Part 284 transportation service must include the following:

 

(a) Gas Quantities: The maximum daily delivery quantity applicable to each

Receipt Point(s) and Delivery Point(s) stated in dekatherms and Mcf and

the estimated total quantities to be received and transported over the

delivery period.

 

(b) Receipt/Delivery Point: The designated Primary Receipt Point(s) and

Primary Delivery point(s) for the requested transportation together with

the name and entity delivering gas to Transporter and the name of the

entity to receive the gas from Transporter.

 

(c) Term: The proposed commencement and termination dates of service.

 

(d) Shipper Certification: A statement by the Shipper certifying that all

necessary upstream and downstream arrangements will be in place on the

date the transportation service is to commence and that Shipper will have

title or the right to acquire title to the gas to be delivered to

Transporter.

 

(e) Facilities: Identification and location of any facilities to be

constructed or installed by any party affected by the proposed

transportation service.

 

No request for transportation service will be entered on Transporter's log, as

required by Section 284.13 of the Commission's Regulations, or scheduled for

receipt and delivery until the required information has been provided.