Tennessee Gas Pipeline Company
FIFTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2004, Docket: RP04-355-000, Status: Effective
First Revised Sheet No. 382 First Revised Sheet No. 382 : Effective
Superseding: Original Sheet No. 382
GENERAL TERMS AND CONDITIONS (continued)
XXI. RESEARCH, DEVELOPMENT AND DEMONSTRATION RATE ADJUSTMENT
The rates for Transporter's jurisdictional services shall be adjusted from time
to time to reflect changes in Transporter's expenditures for Research,
Development and Demonstration (RD&D), in accord with the procedures herein
specified.
1. Filing of RD&D Rate Adjustment
1.1 Effective Rate after RD&D Rate Adjustment: The effective rates
under Transporter's Rate Schedules as reflected in the Summary of
Rates and Charges in Volume No. 1 of Transporter's FERC Gas Tariff
shall be the Rates After Current Adjustment for each applicable
rate schedule reflecting the Current RD&D Rate Adjustment under
this Article XXI.
1.2 Effective Date of Adjustment: The Effective Date of Adjustment
for each Current RD&D Rate Adjustment filed pursuant to Section 2
hereof shall be the date specified in Transporter's filing and
shall be the first day of a month; provided, however, that Current
RD&D Rate Adjustments shall be made effective no more frequently
than semiannually. The Current RD&D Rate Adjustment shall become
effective on the Effective Date of Adjustment without suspension;
provided, however, that such Current RD&D Rate Adjustment shall be
subject to reduction and refund of any portion found after hearing
to be unjustified by a final and nonappealable Commission order.
Any refunds under this Article shall include simple interest at
the interest rate specified in Section 154.67 of the Commission's
Regulations under the Natural Gas Act.
1.3 Filing Procedure: At least thirty days prior to the Effective
Date of Adjustment, Transporter shall file with the Federal Energy
Regulatory Commission and post, as defined by Section 154.16 of
the Commission's Regulations, revised Tariff Sheets showing for
each of Transporter's applicable Rate Schedules, the Base Tariff
Rates and the Rates After Current Adjustment reflecting the
Current RD&D Rate Adjustment determined in accord with this
Article. Such filing shall include (1) detailed computations
showing clearly the derivation of such current RD&D Rate
Adjustment and (2) a statement as to the anticipated scope and
objective of the RD&D and the relationship of such objective to
the service for which the RD&D adjustment is to apply. Such
supporting data shall be in lieu of any other data or supporting
materials required by the Commission's Regulations under the
Natural Gas Act. The filing by Transporter, or the making
effective, of rate changes under procedures other than this
Article shall have no effect upon the right and duty of
Transporter to make changes under this Article.