Tennessee Gas Pipeline Company
FIFTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2008, Docket: RP04- 99-004, Status: Effective
Second Revised Sheet No. 305A Second Revised Sheet No. 305A : Effective
Superseding: First Revised Sheet No. 305A
GENERAL TERMS AND CONDITIONS (continued)
35. The term "Daily Variance" or "Daily Imbalance" shall have the meaning set forth
in Section 7 of Rate Schedule LMS-MA and Section 5 of Rate Schedule LMS-PA.
36. The term "Hydrocarbon Dewpoint" shall mean cricondentherm, the highest temperature
at which the vapor-liquid equilibrium may be present. The Hydrocarbon Dewpoint
(cricondentherm) calculations are performed using the Peng-Robinson equation of
state.
37. The term "HDP Segment(s)" shall have the meaning as defined in Article II,
Section 3.1.
38. The term "HDP Problem(s)" shall mean actual or anticipated operational
problems on Transporter's system or at its Interconnects with interstate or
intrastate pipelines, storage facilities, end users, and local distribution
companies specifically related to actual or anticipated hydrocarbon liquid
fallout. The term "Interconnect," in this context solely, shall mean the
integrated metering, measurement, pressure regulation and gas handling
facilities and other equipment ("Interconnect Equipment") located within the
measurement/delivery complex where Transporter delivers gas to an interstate
or intrastate pipeline, end user, storage facility or local distribution
company, typically contained within a fenced or other secure enclosure.
Interconnect Equipment may or may not be owned by Transporter and may or may
not be located before the meter demarcating the change in possession of the
gas.
II. QUALITY
1. The provisions set forth in this Article II Section 1 shall apply to all gas
delivered by Transporter under this FERC Gas Tariff.
(a) Heating value: The natural gas shall have a total heating value of not
less than nine hundred and sixty-seven British thermal units per cubic
foot. Transporter, in its own right or in accord with the instructions
of Shipper, may subject, or permit the subjection of, the natural gas to
compression, cooling, cleaning and other processes and helium, natural
gasoline, butane, propane, and any other hydrocarbons except methane may
be removed prior to delivery to Shipper. Title to the products will
remain with party that has contracted for the processing rights and
notified Transporter of such contract; otherwise, title to the products
will remain with Transporter. In the event that the total heating value
of gas, per cubic foot, in any month