Tennessee Gas Pipeline Company
FIFTH REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/2008, Docket: RP08-338-000, Status: Effective
Sixth Revised Sheet No. 220 Sixth Revised Sheet No. 220 : Pending
Superseding: Fifth Revised Sheet No. 220
NET-284 RATE SCHEDULE (continued)
4.4 Secondary Delivery Points: A Shipper under this rate schedule may use as
a secondary delivery point any eligible delivery point on Transporter's
system which is within the Transportation Path as defined in Section
6.1(h) of this Rate Schedule.
4.5 Contract Quantities at Delivery Points: The sum of the maximum daily
delivery quantities applicable to all of Shipper's Primary Delivery
Points may not exceed the maximum daily quantity under the Shipper's
Service Agreement.
4.6 Change of Primary Points: Subject to agreement by Transporter and in
accordance with Article XXVIII of the General Terms and Conditions of
Transporter's FERC Gas Tariff, a Shipper may elect to substitute new
points for the Primary Delivery or Primary Receipt Points in its
Transportation Service Agreement. Such changes may be affected by prior
notice to Transporter of 30 days if in writing or 15 days if by PASSKEY.
All such changes must be reflected in an amended Transportation Service
Agreement and shall be effective at the commencement of the following
month unless otherwise agreed by Transporter. Transporter shall not be
required to accept an amendment if there is inadequate capacity available
to render the new service or if the change would reduce the reservation
charges applicable to the Transportation Service Agreement.
4.7 Extended Receipts: Shipper may use points not in its Transportation Path
as defined in Section 6.1(h) of this Rate Schedule subject to the
priority specified in Section 5(d) of Article III of the General Terms
and Conditions. In order to use such points, Shipper must request
Extended Receipt Service by nominating in PASSKEY the following
information: (i) the point at which Shipper desires to receive gas, and
(ii) the requested quantity to be received at the point. Termination of
the underlying agreement shall terminate any Extended Receipt Service.
This service will be subject to an additional usage charge as specified
in the Summary of Rates and Charges in Transporter's effective FERC Gas
Tariff.
4.8 Extended Deliveries: Shipper may use points not in its Transportation
Path as defined in Section 6.1(h) of this Rate Schedule subject to the
priority specified in Section 5(d) of Article III of the General Terms
and Conditions. In order to use such points, Shipper must request
Extended Delivery Service by nominating in PASSKEY the following
information: (i) the point at which Shipper desires to deliver gas, and
(ii) the requested quantity to be delivered at the point. Termination of
the underlying agreement shall terminate any Extended Delivery Service.
This service shall be subject to an additional usage charge as specified
in the Summary of Rates and Charges in Transporter's effective FERC Gas
Tariff.
5. FUEL AND USE
5.1 Shipper shall provide daily to Transporter, at no cost to Transporter,
the quantity of gas required for Transporter's system fuel and uses and
gas lost and unaccounted for ("Fuel and Use Quantity"), associated with
rendering transportation service pursuant to this Rate Schedule.
Shipper shall make available to Transporter from the Transportation
Quantity the amount of gas equal to the Fuel and Use Quantity, which
will be equal to the quantity of gas scheduled for delivery to
Transporter multiplied by the applicable percentage shown for each
Shipper's service as stated below: