RATE SCHEDULE FT-A

FIRM TRANSPORTATION SERVICE (continued)

 

 

2.3 Transporter shall not be required to transport gas where the total

quantity of gas scheduled for transportation is less than that required to

operate existing compression facilities necessary to provide the

transportation service.

 

3. QUALIFICATION FOR SERVICE

 

3.1 All Shippers requesting firm transportation service must qualify pursuant

to Article XXVIII of the General Terms and Conditions of Transporter's

FERC Gas Tariff.

 

3.2 All Shippers requesting firm transportation service must execute a

Transportation Service Agreement in accord with the provisions of Article

XXVIII of the General Terms and Conditions of Transporter's FERC Gas

Tariff.

 

4. DELIVERY AND RECEIPT POINTS; PRESSURE; UNIFORM QUANTITIES

 

4.1 Primary Receipt Points: Subject to the availability of capacity, any

receipt point on Transporter's system, including storage service points

and Pooling Area Points, shall be eligible for designation as a Primary

Receipt Point for gas transported under this Rate Schedule. Transporter

shall not be required under any circumstances to receive gas at any

Receipt Point where the total quantity of gas for transportation

scheduled for receipt on any day is less than that required for the

accurate measurement of quantities to be received. With regard to

Transportation Contracts entered into after June 25, 1991, Shipper shall

be required to notify Transporter if both (i) a Shipper does not deliver

gas at a Primary Receipt Point that is capacity constrained at an average

daily quantity greater than 30% of Shipper's maximum daily quantity at

that receipt point under Shipper's Transportation Contract under this

Rate Schedule over any twelve calendar month period and (ii) the Shipper

does not have a gas supply contract at that point which has demand, take-

or-pay, deficiency or other fixed charge obligations.