Tennessee Gas Pipeline Company

FIFTH REVISED VOLUME NO. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 08/01/1995, Docket: RP95-112-009, Status: Effective

Second Sub 2nd Revised Sheet No. 95A Second Sub 2nd Revised Sheet No. 95A : Effective

Superseding: 1st Revised Sheet No. 95A

 

 

RATE SCHEDULE FS

 

FIRM STORAGE SERVICE (continued)

 

3.2 Natural gas receipts and redeliveries by Transporter under this Rate

Schedule shall not be subject to curtailment or interruption or

discontinuance, except as may be excused in accordance with Article X of

the General Terms and Conditions of the FERC Gas Tariff. Such curtailment

or interruption shall be imposed upon Shippers in accordance with Article

III, Section 6 of the General Terms and Conditions of the FERC Gas Tariff.

Conditional Deliverability entitlements shall be subject to the conditions

of Section 3.4 of this Rate Schedule.

 

3.3 The quantity of gas in Shipper's FS storage account at any time shall be

Shipper's Storage Balance at that time and shall not exceed Shipper's

Maximum Storage Quantity ("MSQ"). Transporter shall be ready at all times

to redeliver to Shipper and Shipper shall have the right at all times to

receive from Transporter natural gas at daily rates up to the Maximum

Daily Withdrawal Quantity, provided that the withdrawal quantity equals

the FS gas scheduled for transportation pursuant to Shipper's

transportation agreements with Transporter or with a third party

transporter, as applicable, from the FS Service Point.

 

Transporter shall accept in any one day for injection into Transporter's

underground storage facilities for Shipper's account a quantity of gas

equal to Shipper's Maximum Daily Injection Quantity, except as provided in

Section 7.1 of this Rate Schedule. Transporter shall withdraw in any one

day from Transporter's underground storage facilities for Shipper's

account a quantity of gas equal to Shipper's Maximum Daily Withdrawal

Quantity as determined in Section 3.4 of this Rate Schedule.

 

3.4 A shipper electing Conditional Deliverability entitlements shall have

Conditional Deliverability stated in its Service Agreement in separate

Ratchet 0, I and II quantities. The following conditions shall apply to

Shipper's withdrawal rights utilizing Conditional Deliverability.

 

(a) Withdrawal Level Inventory Level

 

Ratchet 0 > 30% - 100%

Ratchet I > 20% - 30%

Ratchet II > 0% - 20%

 

Inventory level is the ratio of Shipper's Storage Balance to Shipper's

Maximum Storage Quantity.

 

(b) Shipper shall maintain a minimum Storage Balance greater than or

equal to 15% of its Maximum Storage Quantity from November 1 to March

1. Customers withdrawing below the minimum Storage Balance prior to