Central Kentucky Transmission Company
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/01/2006, Docket: CP05- 48-002, Status: Effective
Original Sheet No. 92 Original Sheet No. 92 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
(b) Rate Schedule ITS and Overrun Quantities Under Rate Schedule FTS.
(1) Where requested deliveries at the same highest rate exceed
available capacity, Transporter shall allocate capacity first to those
Shippers flowing gas on a pro rata basis, based upon respective
confirmed nominations; and second to all remaining Shippers based upon
the order in which Transporter received nominations from those Shippers
(equally to any Shippers submitting nominations on the same day).
(2) If intraday nominations require an allocation of the
pipeline system, the following will describe the circumstances that
allow a higher priority service to bump a lower priority service.
(a) Evening Nomination Cycle: For nominations received by
6:00 p.m. CT and to be effective at the start of the upcoming Gas
Day, nomination increases submitted under Rate Schedule FTS will
have priority over nominated and scheduled quantities under Rate
Schedule ITS and overruns under the firm rate schedule and may
bump such quantities effective at 9:00 a.m. CT the next day.
Nomination increases submitted under Rate Schedule ITS and
overruns under the firm rate schedules shall be subject to
available unscheduled capacity and will not bump scheduled
quantities. Transporter shall notify Shippers being bumped as a
result of intraday nominations by 10:00 p.m. C.T.