Central Kentucky Transmission Company

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 05/01/2006, Docket: CP05- 48-002, Status: Effective

Original Sheet No. 92 Original Sheet No. 92 : Effective

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

(b) Rate Schedule ITS and Overrun Quantities Under Rate Schedule FTS.

 

(1) Where requested deliveries at the same highest rate exceed

available capacity, Transporter shall allocate capacity first to those

Shippers flowing gas on a pro rata basis, based upon respective

confirmed nominations; and second to all remaining Shippers based upon

the order in which Transporter received nominations from those Shippers

(equally to any Shippers submitting nominations on the same day).

 

(2) If intraday nominations require an allocation of the

pipeline system, the following will describe the circumstances that

allow a higher priority service to bump a lower priority service.

 

(a) Evening Nomination Cycle: For nominations received by

6:00 p.m. CT and to be effective at the start of the upcoming Gas

Day, nomination increases submitted under Rate Schedule FTS will

have priority over nominated and scheduled quantities under Rate

Schedule ITS and overruns under the firm rate schedule and may

bump such quantities effective at 9:00 a.m. CT the next day.

Nomination increases submitted under Rate Schedule ITS and

overruns under the firm rate schedules shall be subject to

available unscheduled capacity and will not bump scheduled

quantities. Transporter shall notify Shippers being bumped as a

result of intraday nominations by 10:00 p.m. C.T.