GENERAL TERMS AND CONDITIONS
(Continued)
(c) Priority of Firm Storage Under Agreements: All firm
Storage Agreements shall have equal priority as to
service, and shall have priority over interruptible
Storage Services under Rate Schedule IS and Overrun
Service.
10.2 INTERRUPTIBLE AND OVERRUN STORAGE
(a) Priority Of Nominations For Interruptible and Overrun
Service: Seller, in determining the allocation of
interruptible and overrun service capacity on any Day
among Customers under Rate Schedule IS and Rate Schedule
FS, which have nominated quantities of service desired on
such Day, shall be assigned the order of priority of such
service on the basis that the highest rate offered for
such service shall be accorded the highest priority. If
more than one nomination or request for interruptible and
overrun storage on a Day includes an offer of the same
rate, then the order of priority as among such
nominations or requests shall be the same. If capacity is
constrained, service among Customers within the same
priority will be allocated pro rata based upon the
quantities nominated or requested.
(b) A Customer desiring Interruptible or Overrun service
under Rate Schedule IS or Rate Schedule FS in a Month
shall submit to Seller, at least five (5) business Days
prior to the start of such Month, the rate that such
Customer is willing to pay for such service in such
Month. The rate submitted by Customer pursuant to the
above provision shall be used to determine priority among
nominations on each Day of such Month. Once Customer's
nomination is accepted, and priority is assigned thereto
pursuant to this section for such Month, such priority
shall not be changed by the execution of new IS
Agreements during the Month for service under Rate
Schedule IS or the nomination of additional Overrun